printer friendly versionBack to Ball Park Estimates

“Ballpark” Price Estimates

Radiantec Company has the most competitive prices in the industry!


Photograph of a Ballpark


Use these figures for preliminary cost estimates for your various options.

Cost for Underfloor Materials


WITHIN JOISTED FLOOR SYSTEMS
(including tubing, heat emission plates and fittings)
(Typical labor allotment/joisted floors 12-16 hours per 1000 sq. ft.)


Using 7/8" PEX Tubing

  • Typical floor $0.85 per square ft floor area
  • Carpeted / high heat loss areas $1.00 per square ft floor area

Using 1/2" PEX Tubing

  • Typical floor $1.25 per square ft floor area
  • Carpeted / high heat loss areas $1.50 per square ft floor area

WITHIN "SLAB" FLOORS (on grade, suspended or lightweight)
includes tubing, typical manifolds, and tying materials
(Typical labor allotment/slab floors 8 hours per 1000 sq. ft.)


Using 7/8" PEX Tubing

  • $0.70 per sq ft floor area

Using 1/2" PEX Tubing

  • $0.80 per sq ft floor area

LARGE COMMERCIAL PROJECTS
(Typical labor allotment
4 hours per 1000 sq. ft.)

  • $0.50per sq ft floor area

COST FOR HEATING ZONES


FOR "CLOSED SYTEMS" (using cast iron pumps).
(includes thermostat, relay control, pump and other mechanicals)
(Typical labor allotment 8-16 hours for one (1) zone
3 additional hours per additional zone)


Within Slabs

  • $550-700 for one zone
  • $1100-1250 for two zones
  • $300-400 for each added zone after two add

Within Joisted Floors

  • $550-700 for one zone
  • $1100-1250 for two zones
  • $300-400 for each added zone after two add

FOR "OPEN SYSTEMS"(using stainless pumps).
(includes thermostat, relay control, pump, and other mechanicals)
(Typical labor allotment 8-16 hours for one (1) zone
3 additional hours per additional zone)


Within Slabs

  • $450-600 for one zone
  • $1100-1250 for two zones
  • $300-400 for each added zone after two add

Within Joisted Floors

  • $450-600 for one zone
  • $1100-1250 for two zones
  • $300-400 for each added zone after two add